Design-build electrical for a refrigerated distribution facility in the Greater Houston area. Medium-voltage service entrance, ammonia refrigeration plant power, ASRS-integrated distribution, and BMS commissioning on a 14-month schedule.
Refrigerated distribution facility with -20°F freezer space, 35°F cooler space, and an attached dry-storage and dock area.
180,000 SF refrigerated, 50,000 SF dry, 20,000 SF office and dock. 38 dock doors with refrigerated trailer plug-in capacity.
Three screw compressor packages, central machine room, evaporative condensers in roof-mounted yard. Refrigeration plant power on dedicated MCC.
CenterPoint Energy primary service, pad-mount switchgear, 2,500kVA service transformer. Service entrance sized with growth headroom for future ASRS expansion.
Preconstruction engagement during refrigeration consulting engineer design development. Single accountable contractor through energization and commissioning.
Long-lead switchgear and MV cable released during DD. Critical path was utility coordination, not electrical field labor.
Cold storage projects rarely have schedule slack. The owner had a contractual energization date driving a 14-month build window, with refrigeration commissioning required to begin within 12 months of NTP. The critical-path constraint wasn’t field labor — it was utility coordination and long-lead switchgear procurement.
We engaged the utility transmission planning group during design development, before construction documents were issued. Long-lead MV switchgear and the service transformer were released during DD with the owner’s approval, six months earlier than typical plan-and-spec procurement. The refrigeration plant MCC was prefabricated off-site and delivered to the building shell before envelope close-in.
Energization completed on schedule. Refrigeration plant commissioning began on the contracted date, with the plant operating at design capacity within 4 weeks of energization. Owner’s operations team accepted the closeout package without electrical punchlist carryover into year-one operations.
Send us your refrigeration load study, site plan, and target energization. We’ll come back with a preconstruction estimate.