Case Study · Houston, TX · Cold Storage

250,000 SF Cold Storage Facility

Design-build electrical for a refrigerated distribution facility in the Greater Houston area. Medium-voltage service entrance, ammonia refrigeration plant power, ASRS-integrated distribution, and BMS commissioning on a 14-month schedule.

Project at a glance

Sector

Cold Storage · 3PL Refrigerated Distribution

Refrigerated distribution facility with -20°F freezer space, 35°F cooler space, and an attached dry-storage and dock area.

Size

250,000 SF total

180,000 SF refrigerated, 50,000 SF dry, 20,000 SF office and dock. 38 dock doors with refrigerated trailer plug-in capacity.

Refrigeration

1,800 tons ammonia (R-717)

Three screw compressor packages, central machine room, evaporative condensers in roof-mounted yard. Refrigeration plant power on dedicated MCC.

Service entrance

25kV class, 3,000A at 480V secondary

CenterPoint Energy primary service, pad-mount switchgear, 2,500kVA service transformer. Service entrance sized with growth headroom for future ASRS expansion.

Delivery

Design-build

Preconstruction engagement during refrigeration consulting engineer design development. Single accountable contractor through energization and commissioning.

Schedule

14 months NTP to energization

Long-lead switchgear and MV cable released during DD. Critical path was utility coordination, not electrical field labor.

Scope delivered

  • Utility coordination & MV service. 25kV class primary service from CenterPoint Energy, pad-mount switchgear with primary metering, and a 2,500kVA pad-mount service transformer. Service entrance sized at 3,000A / 480V secondary with documented growth headroom for the operator’s planned ASRS expansion in year 3.
  • Refrigeration plant power. Dedicated MCC for the ammonia refrigeration plant supporting three screw compressor packages, evaporative condenser fan motors, and refrigerant pump skids. VFDs on compressor leads for capacity control. Refrigerant detection wiring, machinery room ventilation interlocks, and emergency stop circuits per IIAR 2 and ASHRAE 15.
  • Cold-space distribution. Branch panelboards inside the refrigerated envelope rated for sub-freezing ambient. NEC 310.15 ampacity adjustments applied to conductors in cold rooms. Vapor-tight LED fixtures throughout, sealed device boxes, and condensation-tolerant termination methods.
  • ASRS & material handling. Power distribution for the unit-load ASRS at the back of the freezer envelope, with coordination of scope splits with the ASRS integrator. VFDs on conveyor drives, MCC for material-handling motors, and PLC interfaces to the warehouse management system.
  • Dock & loading bay power. 38 dock doors with leveler, vehicle restraint, and dock light power. Refrigerated trailer plug-in receptacles (480V 3-phase) at each dock position with metering for cold-chain billing.
  • BMS integration. Building management system interfaces to refrigeration plant (Danfoss AK-SM platform), HVAC for dry-storage and office, dock door interlocks, and lighting control. BACnet and Modbus TCP tie-ins through the BMS contractor.
  • Life-safety systems. NFPA 70 Article 700 emergency power, NFPA 110 generator installation sized for refrigeration plant restart sequences plus life-safety load. Egress lighting rated for cold-temperature operation in freezer spaces.

The challenge

Cold storage projects rarely have schedule slack. The owner had a contractual energization date driving a 14-month build window, with refrigeration commissioning required to begin within 12 months of NTP. The critical-path constraint wasn’t field labor — it was utility coordination and long-lead switchgear procurement.

We engaged the utility transmission planning group during design development, before construction documents were issued. Long-lead MV switchgear and the service transformer were released during DD with the owner’s approval, six months earlier than typical plan-and-spec procurement. The refrigeration plant MCC was prefabricated off-site and delivered to the building shell before envelope close-in.

The outcome

Energization completed on schedule. Refrigeration plant commissioning began on the contracted date, with the plant operating at design capacity within 4 weeks of energization. Owner’s operations team accepted the closeout package without electrical punchlist carryover into year-one operations.

Explore further

Cold storage project of your own?

Send us your refrigeration load study, site plan, and target energization. We’ll come back with a preconstruction estimate.

Text us