Electrifying a Class 8 truck fleet doesn’t end at "buy some chargers." The utility service implications, the distribution build-out, and the operational coordination determine whether the electrification plan actually works or quietly stalls at vehicle three.
A Class 8 electric truck pulls 350–500kW during DC fast charging. Most warehouse operators we’ve worked with significantly underestimate this when they first consider electrification. A typical 750,000 SF distribution center built five years ago has a 3,000A service at 480V — about 2.5MW of total capacity. Add 10 fast-charging stalls and you’ve consumed 100% of that capacity during peak charging windows, leaving zero for the lighting, refrigeration, ASRS, dock equipment, and office that the building was originally designed for.
This is why "we’ll add EV charging later" frequently means "we’ll trigger a service entrance upsize and a utility coordination cycle that adds 6–18 months and several million dollars to the project." Better to plan the load math during initial design, even if buildout is staged.
350–500kW per stall during charging. Charging windows are typically 30–90 minutes for highway tractors, longer for terminal tractors that may stay plugged-in overnight. Connector types are converging on CCS1 in North America with NACS adapter compatibility increasingly required. Equipment manufacturers include ChargePoint, ABB, Heliox, Tritium, and BTC Power. Pricing is highly variable.
Typical yard tractor electrification uses lower power (50–150kW). Yard tractors run continuous shift work and benefit from opportunity charging during dock-side dwell time. Charge management software is more important here than peak charger power.
Last-mile delivery vans, fleet sedans, and pickups typically use Level 2 charging at 7–19kW per stall. These are the cheapest chargers and the lowest impact on facility electrical load. A typical fleet of 30–50 vans can be supported with Level 2 infrastructure totaling 200–500kW of demand.
Level 2 chargers in employee parking. Typically 7–11kW per stall. Used overnight or during workday parking. Often subsidized by utility incentive programs. Lowest load impact, highest visibility for sustainability reporting.
For warehouse operators planning electrification — either at new construction or as a retrofit at an existing site — a few things should land in early planning rather than waiting for charger purchase:
Operators treat EV charging like a parking lot amenity and let it land in the project late, as a value-engineering line item. By the time the actual charger procurement happens, the building’s electrical infrastructure has been finalized with no provisions for the load. Three options at that point:
None of these are good outcomes. All three are avoidable by getting the load math right during early design.
If you’re a fleet operator evaluating warehouse sites for lease and you plan to electrify within the lease term, ask the building owner’s engineering team specifically:
These questions during lease evaluation will tell you whether the site supports your electrification plan within the lease term — or whether you’ll need a different building.
Send us your site, fleet plan, and target electrification timeline. We’ll engage on load study and utility coordination during preconstruction.